Dexter District Library
New Library

Program Calendar

CalendarView and print the current calendar(s) by clicking here.

Newsletter

Ex Libris NewsletterWant to catch up on the latest news at your library? Click here to view our Ex Libris Newsletter(s).

Search the Catalog

Search this Site

Questions?

Ask a Librarian

Have a question? Get it answered here for free!

MeL Databases

MeL Databases

MeL Databases contain full-text articles from magazines, journals and newspapers as well as digital books. Click here to familiarize yourself with these databases.

Construction Phases

Construction phases listed below are a rough estimate. As confirmed dates become available, we will list them accordingly.

Winter 2006-07

  • Finalize value engineering
  • Finalize construction documents
  • Site plan bidding
  • Permit approval

Spring 2007

  • Demolition of existing houses
  • Ground breaking
  • Site work

Summer 2007

  • Begin construction
    (construction to last est. 13 months)
  • Built underground water retention system for parking lot and associated retaining wall

Fall 2007

  • Finished parking area for construction work space
  • Excavation for foundations
  • Site survey and layout for foundations
  • Concrete footers and reinforcing steel set
  • Foundation concrete poured

Winter 2007 - 2008

  • Masonry for stairwells and elevator shaft installed
  • Structural steel installation began