Construction Phases
Construction phases listed below are a rough estimate. As confirmed dates become available, we will list them accordingly.
Winter 2006-07
- Finalize value engineering
- Finalize construction documents
- Site plan bidding
- Permit approval
Spring 2007
- Demolition of existing houses
- Ground breaking
- Site work
Summer 2007
- Begin construction
(construction to last est. 13 months) - Built underground water retention system for parking lot and associated retaining wall
Fall 2007
- Finished parking area for construction work space
- Excavation for foundations
- Site survey and layout for foundations
- Concrete footers and reinforcing steel set
- Foundation concrete poured
Winter 2007 - 2008
- Masonry for stairwells and elevator shaft installed
- Structural steel installation began